How Do They Grow?
Tower cranes arrive at the construction site on 10 to 12 tractor-trailer rigs. The crew uses a mobile crane to assemble the jib and the machinery section, and places these horizontal members on a 40-foot (12-m) mast that consists of two mast sections. The mobile crane then adds the counterweights.The mast rises from this firm foundation. The mast is a large, triangulated lattice structure, typically 10 feet (3.2 meters) square. The triangulated structure gives the mast the strength to remain upright.
![]() |
![]() |
![]() |
To rise to its maximum height, the crane grows itself one mast section at a time! The crew uses a top climber or climbing frame that fits between the slewing unit and the top of the mast. Here's the process:
- The crew hangs a weight on the jib to balance the counterweight.
- The crew detaches the slewing unit from the top of the mast. Large hydraulic rams in the top climber push the slewing unit up 20 feet (6 m).
- The crane operator uses the crane to lift another 20-foot mast section into the gap opened by the climbing frame. Once bolted in place, the crane is 20 feet taller!
![]() |
![]() |
Once the building is finished and it is time for the crane to come down, the process is reversed -- the crane disassembles its own mast and then smaller cranes disassemble the rest.